St. Charles Moves Forward with Roadway and Plaza Projects
- Sep 8
- 2 min read
The St. Charles Government Operations Committee convened on September 28, 2023, focusing on key community infrastructure and development initiatives. The meeting featured discussions and approvals for the Reserves Roadway Paving Project, street closures for the Fire Department Open House, and progress updates on the First Street Plaza Project.
Fire Department Open House Street Closures Approved
Chief Swanson presented a request to close several streets to accommodate the upcoming Fire Department Open House.
Approved closures: Lot J, State Park, and First Avenue (between Cedar and State)
Duration: 6:00 AM to 5:00 PM
The motion passed unanimously, ensuring public safety while allowing residents to participate in the community event.
Reserves Roadway Paving Project Reconsidered and Approved
The committee revisited the Reserves Roadway Paving Project following new information that prompted reconsideration of a previously failed vote. Russell Kobe detailed the importance of completing the project before winter to address significant maintenance issues.
Project Overview
Total Estimated Cost: $385,000
Letter of Credit: $343,000 held by the city
Scope:
Curb repair
Driveway apron repairs
Removal and replacement of deteriorated base pavement
Final surface course installation
Financial Considerations
A $42,000 potential gap exists between the LCO amount and current estimates. Options to reduce costs include:
Repairing curbs instead of replacing them
Exploring alternative construction methods to optimize spending without compromising quality
Committee Discussion
Alderman Lindsey emphasized the city’s responsibility to complete the roadway as a public right-of-way and ensure resident safety.
Other aldermen agreed, highlighting recent street issues exacerbated by rainfall.
Decisions Made
Authorized the Mayor to demand payment under the Letter of Credit
Approved the construction contract for the project
Staff will continue analyzing cost-saving measures and report updates to City Council
First Street Plaza Project Update
Heather and Peter Stewart provided a detailed progress report on the Saint Charles Initiative / First Street Plaza Project.
Funding and Donations
Total donations raised: $1.534 million
Additional $66,000 received since March
Construction Progress
Underground work: Complete
Concrete pours: Ongoing
Paver system: Scheduled within 4–5 weeks
Vertical elements (kiosks, benches): Foundations progressing
Large trellis structure: Fabricated and awaiting coating, installation expected in late October/November
Landscaping: Expected to begin in 3–4 weeks
The project remains on track for substantial completion by January 1, 2024, though some technology and lighting installations may extend beyond that date.
Action Items and Next Steps
Staff to provide definitive numbers on potential cost reductions for the Reserves Roadway Paving Project
Review policies to prevent similar financial guarantee issues in future development projects
Provide a more comprehensive update on First Street Plaza construction to Government Services
Conclusion
The September 28 meeting showcased St. Charles’ commitment to community safety, infrastructure improvements, and downtown development. By approving the Reserves Roadway Paving Project and advancing the First Street Plaza Project, the city is ensuring residents benefit from well-maintained roadways and enhanced public spaces. The city continues to balance fiscal responsibility with timely completion of essential projects, while engaging with residents and stakeholders throughout the process.


Comments